Dated milestones from the sources indexed; partial dates (year, quarter) are shown as published.
No dated milestone has been published for this project yet.
A California judge says Imperial County must review a proposed 330 MW data center and its power, water, battery, and generation infrastructure.
Primary source: datacenterknowledge.com
Location as published; no coordinates yet.
Every field with its source, observation dates, confidence and extraction method.
| Field | Value | Source | Confidence |
|---|
| Acreage | 75 | Data Center KnowledgeNews | Moderate |
| Announced | Sep 1, 2026 | Data Center KnowledgeNews | Moderate |
| Country | US | Data Center KnowledgeNews | Moderate |
| Description | A California judge says Imperial County must review a proposed 330 MW data ce… | Data Center KnowledgeNews | Moderate |
| Name | MW Data Center | Data Center KnowledgeNews | Moderate |
| Planned power | 330 MW | Data Center KnowledgeNews | Moderate |
| Region | California | Data Center KnowledgeNews | Moderate |
| Source Url | https://www.datacenterknowledge.com/data-center-construction/california-judge… | Data Center KnowledgeNews | Moderate |
| Status | proposed | Data Center KnowledgeNews | Moderate |
Detected events on this project.
When each source was observed, changed or verified.