Dated milestones from the sources indexed; partial dates (year, quarter) are shown as published.
A 15-year, 300 MW hyperscaler lease at Delta Forge 1 underscores the shift to purpose-built AI infrastructure backed by investment-grade tenants and scalable financing.
Primary source: datacenterfrontier.com
Location as published; no coordinates yet.
Every field with its source, observation dates, confidence and extraction method.
| Field | Value | Source | Confidence |
|---|---|---|---|
| Acreage | 500 | Data Center FrontierNews | Moderate |
| Announced | May 4, 2026 | Data Center FrontierNews | Moderate |
| Country | US | Data Center FrontierNews | Moderate |
| Description | A 15-year, 300 MW hyperscaler lease at Delta Forge 1 underscores the shift to… | Data Center FrontierNews | Moderate |
| Expected opening | 2027 | Data Center FrontierNews | Moderate |
| Investment | $7.5B | Data Center FrontierNews | Moderate |
| Name | Applied Digital data center project (US) | Data Center FrontierNews | Moderate |
| Operator | Applied Digital | Data Center FrontierNews | Moderate |
| Planned power | 300 MW | Data Center FrontierNews | Moderate |
| Source Url | https://www.datacenterfrontier.com/hyperscale/article/55373280/300-mw-hypersc… | Data Center FrontierNews | Moderate |
| Status | announced | Data Center FrontierNews | Moderate |
Detected events on this project.
When each source was observed, changed or verified.